New Brunswick sets ground rules for data centre projects
New Brunswick released a data centre policy on Thursday, saying projects that don't follow it will be rejected. The province will now assess a project's benefits before it reaches NB Power, which reported 10 applications needing up to 900 megawatts combined. Developers must show a net benefit to utilities, consult First Nations through binding agreements, limit environmental impacts and prove they are technically and financially sound. Large projects must register for an environmental impact assessment. The rules cover proposals already under consideration. The province also plans legislative changes on reviewing power supply deals and letting local governments negotiate community benefits.